PROCESS OF TAKING OUT QUANTITIES:-
The quantities like earth work, foundation concrete, brickwork in plinth and super structure etc., can be workout by any of following methods.
a) Long wall - short wall method
b) Center line method
c) Partly center line and short wall method
a) Long wall-short wall method:-
The quantities like earth work, foundation concrete, brickwork in plinth and super structure etc., can be workout by any of following methods.
a) Long wall - short wall method
b) Center line method
c) Partly center line and short wall method
a) Long wall-short wall method:-
long wall short wall method |
In this method, the wall along the length of room is considered to be long wall while the wall perpendicular to long wall is said to be short wall. To get the length of long wall or short wall, calculate first the center line lengths of individual walls. Then the length of long wall, (out to out) may be calculated after adding half breadth at each end to its center line length. Thus the length of short wall measured into in and may be found by deducting half breadth from its center line length at each end. The length of long wall usually decreases from earth work to brick work in super structure while the short wall increases. These lengths are multiplied by breadth and depth to get quantities.
b) Center line method:-
center line method |
c) Partly center line and partly cross wall method:-
This method is adopted when external (i.e., around the building) wall is of one thickness and the internal walls having different thicknesses. In such cases, center line method is applied to external walls and long wall-short wall method is used to internal walls. This method suits for different thicknesses walls and different level of foundations. Because of this reason, all Engineering departments are practicing this method.
Some example with problems of Quantity Taking Out Process:-
I. Example 1: From the given figure below calculate the detailed and abstract estimate for the single roomed building (Load bearing type structure) by a) long wall & short wall method (b) Center Line Method.