Huge
amount of money is invested in the construction of buildings bridges and roads.
Economical consideration
needs earliest use of the investment and hence present day demand is automation in
construction. To meet this challenge lot of research has gone into and a number
of techniques are
developed. In this article the automation in buildings, dams, bridges and road
constructions are briefly discussed.
AUTOMATION IN
BUILDING CONSTRUCTION
Digging
for Foundation :- Any
construction work starts with digging for foundation. Nowadays manual digging
for foundation
is almost given up in all cities and towns. JCB is used for this purpose which
can finish digging work for
most of the buildings in a day or two.
Mining,
Lifting, Transporting and Placing of Concrete :- Labour
oriented method of mixing, lifting, transporting and placing of concrete needs
to be changed
to mechanization of concreting. Without it speed and economy cannot be achieved
in construction.
|
Construction automation and Robotics |
Batching
and mixing plants :- In large projects like
dam construction or in ready mixed concrete plants large batching and mixing plants
are used. Ready mixed concreting is new concept in which concrete mixing is
done in large plants
and then transported to needy places in the city. The capacity of such plants
varies from 120-150
cubic metre per hour. These concrete production plant comprise of:
1.
Silos, containers and bins for storage of raw materials.
2.
Batching arrangement.
3.
Measuring and recording equipment.
4. Mixing equipment.
5.
Control system.
6.
Electrical, hydraulic and pneumatic drives.
7.
Conveying systems like belt/screw conveyors.
Cement
is generally stored in silos. The silos are loaded with cement with the help of pneumatic
blowers. If bagged cement is used then tree cement is loaded using compressed
air loader
and a splitter unit.Water is
generally stored in tanks located close to the plant.Aggregates
are stored in silos. A storage capacity of 1500 m3 is
possible.Cement
silos are provided with weigh hoppers which use knife edge balance principle.Larger
plants use electromechanical system.
For measuring water a water meter or a
water batch is used.
The aggregates weighers are generally identical to the cement weighers in the
plant.The
aggregates and cement are first dry mixed in hoppers using scrappers.Provision
is made upto four types of concrete admixtures to be added with required
quantity.Free
fall or power mixers are used for thorough mixing of concrete.Fully
automatic plant control systems with multiple inputs are based in a container
or control room.
Transportation
and Placing :- Various
modes of transporting concrete are truck agitators, truck miners, cranes,
buckets, elevators,belt
conveyors, concrete pumps, chutes etc. The suitability of method of mechanical
transportation varies
from job site to job sites. Often combination of various methods is also used.
It may be noted that truck agitators,
truck miners are useful for horizontal transport, while cranes, buckets,elevators,
belt conveyors and pumps are useful for vertical transport. Chutes are useful
for dropping concrete
in intricate portions.Minibatching
plants are suitable for projects like national
highways, flyover, mass housing and
industrial projects. They have the capacity of 15 to 20 m3
per hour. The plant includes:
1. In
built weighing system for fine and coarse aggregates.
2.
Automated loading system for aggregates.
3.
Cement hopper with weighing system.
4.
Automatic admixture dozing system.
5. Print out system giving
details of batching and mixing.
Self
Compacting Concrete (SCC) :- Self
compacting concrete (SCC) as the name signifies should be able to compact
itself without any additional
vibrations or compaction. It was first developed in late 1980s. It is highly flowable within
the form work and fills it without any external vibration. This is used to
ensure the filling of
congested sections. It includes the high amount of super plasticizers and
cement to increase flowability.
Viscosity agents are also added. The mix may incorporate steel or polypropylene fibres
also. The sand can be finer.In
Sweden bridges are built with SCC. In Japan two anchor blocks were constructed
in Akashi-Kailro
bridge. In France SCC is preferred in cities as noise free concreting. Since
there is no
vibrations in compacting, form works can be reused several time. Use of SCC is
becoming popular in precast
industries also.
Prefabricated
Structural Elements :- Use of
prefabricated structural elements increases construction speed and quality of
structural element.
It saves time because casting of these elements can start much early in
factories much before
they are to be put in the building. For building activity requirement of time
is only for putting
them in the structure. Some of the commonly used prefabricated structural
elements are :
1. Precast concrete portions: Precast
concrete posts and panels of sizes 1000 × 400 × 40 mm
2. Precast
roofing units: In Pune, universal temple of Ramakrishna
was built with suitable elements
to form required geometric forms of Shikharas. The technique of using precast
elements has
saved construction time by at least 6 to 8 months. After erecting shell units
the outer surface of roofs
and domes are covered with Glass Mosaic Tiles laid in polymer modified tile
adhesive,giving excellent aesthetic
view and weather proofing.
3. Lift
slab construction: In this constructions, slabs are cast at
ground level one over the other
with separators in between. Then slabs are lifted along columns to their
positions using cranes
or jacks and clamped. This process has been applied on a two storeyed building
built at Roorkee
by Central Building Research Institute. It is possible to extend the technique
to multistoreyed structures
with several floors. In America this has been tried successfully.
Form
Works :- Providing
form works takes of considerable time in building construction. Convention
method of providing
wooden form work needs modernization. Steel form works consisting of steel
plates,rods and
pipes is gradually replacing conventional wooden form work. Steel form work is
speedy;give
good finished surface and safe too.In the
construction of silos and chimneys slip forms are used. The form work is
clamped to already
built portion of the structure with about 1 to 1.5 m protection. As the upper
portion is built,
form work is slided up and fixed to newly cast portion. It saves cost of form
work and speeds up the construction
activity.
Application
of Robots for Building Automation :- It is
desirable to have robots for building automation to reduce hazards at work
sites, improve quality
and reduce the cost of construction. However there are many problems in the
development of
robots for construction industry such as:
1. Large
loads.
2.
Components of variable sizes to be handled.
3.
Adverse weather conditions such as variable humidity and temperature.
4. Dust
and dirt.
5. Need
for three dimensional movement.
6. Each
site having different size and shape.
Some of
the robotic applications developed are
1. For
inspection of interiors of pipes and drainage conduits.
2. To
detects voids around sewers and offshore pipes.
3. For
excavation for slurry filled foundations.
4.
Human-machine inferface semi automated earth movers.
5.
Concrete cutters and crushers to dismantle concrete structures without creating
noise and air
pollution.
6. For
plastering : An encouraging result has been achieved in this area. Robots that
can plaster
1.0 m2 area with 15 mm plaster in only one minute
have been developed. Manually the same
work needs 30 minute. Sri. B. Srinivas Rao, associate professor, Department of
Civil Engineering,
University College of Engg. Osmania Unversity, Hyderabad reports that for
external plastering
of 15050 m2 area in 11
storey complex with 15 mm thick 1: 4 plaster total cost with robot plastering
worked out Rs. 2,46,988 = 00 whereas it would have cost Rs. 7,09,700 = 00 if
conventional method
was used. The whole work was completed in 9 days only whereas conventional
plastering would
have taken 54 days.Lot of
research and development is required to develop robots for construction works
since nowadays good number of
multistorey buildings are coming up.
AUTOMATION IN
DAM CONSTRUCTION
Dam
construction is highly mechanized. In earthen dam constructions heavy machinery are used for
digging, transporting, placing and consolidating required soil. Concreting is
also highly mechanized.
AUTOMATION IN
BRIDGE CONSTRUCTION
Modern
trend in bridge construction is to use precast construction. Superstructure of
bridge is cast in
parts and erected on the site.Noida
bridge connecting Delhi and Noida provides an eight lane link of 552 m across
river Yamuna.
The superstructure was cast in 13 spans of 42.5 m. Maximum weight of precast
segment was 100
tonnes. Erection was done using launching truss.JJ
hospital flyover in Mumbai is the most elegant and longest elevated road in
India. For this casting
yard could be located at 20 km away from the site. To facilitate transportation
and erection it was
cast in several segments and connected at site.120 m
arch foot bridge across river Seonyce in Seoul, South Korea was built in six
precast segment
and erected at site. Ultra strength concrete (compressive strength 200 N/mm2)
was used for
casting segments.In
Panval Nadi viaduct precast box girders were erected using launching girders
and pushing the girder by jacks.
AUTOMATION IN
ROAD CONSTRUCTION
A number
of machines are used to mix, transport, place, compact and level the asphalt on
super highways. Concreting is
also mechanized in these construction.
0 Comments
For more Information Please Comment